43 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Neelkanth in one paragraph
Neelkanth has a strong delivery record in MahaRERA filings: 87% of registrations needed no extension (38 of 43 analysed Mumbai registrations needed no extension). 5 of 30 under-construction projects are past their original RERA completion date, by 8 months on average (worst 10). The median Neelkanth project scores 46/100 on investment merit (below the Mumbai average); the best, Neelkanth Cottage, scores 64.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Cloud 9 Mumbai region | 10 | 0 | 100% of schedule · — | 0 | 38 |
| Shraddha Panvel / Ulwe / Dronagiri | 10 | 0 | 100% of schedule · — | 0 | 32 |
| West Winds Ghatkopar / Vidyavihar / Vikhroli West | 7 | 0 | 100% of schedule · — | 0 | 58 |
| Adinath Heights Kandivali / Borivali / Dahisar | 7 | 0 | 100% of schedule · — | 0 | 47 |
| Neelkanth Exotica Panvel / Ulwe / Dronagiri | 4 | 2 | 100% of schedule · — | 0 | 29 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Neelkanth projects
All 43 analysed Neelkanth projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Neelkanth Cottage Neelkanth · Ghatkopar / Vidyavihar / Vikhroli West | 64 | 6.4% | 3.4% | 4.5% | ₹20,500 est. | ₹1.33 Cr | Ready |
| Neelkanth Dham Neelkanth · Kharghar / Taloja / Kamothe | 63 | 9.8% | 5.7% | 9.5% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2029 |
| Neel Amplus Neelkanth · Kharghar / Taloja / Kamothe | 63 | 9.8% | 5.5% | 9.3% | ₹9,300 est. | ₹60.5 L | Under construction Apr 2030 |
| One Vaviya Neelkanth · Kharghar / Taloja / Kamothe | 63 | 9.8% | 5.7% | 9.5% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2029 |
| Neelkanth Palm President Neelkanth · Airoli / Ghansoli / Koparkhairane | 62 | 8.5% | 4.0% | 6.7% | ₹11,450 est. | ₹74.4 L | Under construction Dec 2029 |
| Neelkanth Palm Avenue Neelkanth · Airoli / Ghansoli / Koparkhairane | 62 | 8.5% | 4.0% | 6.7% | ₹11,450 est. | ₹74.4 L | Under construction Dec 2029 |
| Zen Neelkanth · Thane West | 58 | 7.5% | 2.7% | 3.6% | ₹12,500 est. | ₹81.3 L | Under construction Dec 2026 |
| West Winds Neelkanth · Ghatkopar / Vidyavihar / Vikhroli West | 58 | 7.1% | 3.1% | 4.1% | ₹19,250 est. | ₹1.25 Cr | Under construction Mar 2026 |
| Lakeview Neelkanth · Thane West | 58 | 7.1% | 3.6% | 4.7% | ₹13,300 est. | ₹86.5 L | Ready |
| The Palm Meridian Neelkanth · Vashi / Sanpada / Nerul / Belapur | 58 | 8.3% | 4.8% | 8.8% | ₹13,550 est. | ₹88.1 L | Under construction Dec 2031 |
| F Neelkanth Greens Neelkanth · Thane West | 56 | 7.9% | 3.4% | 5.1% | ₹12,500 est. | ₹81.3 L | Under construction Mar 2028 |
| Neelkanth Alpine Neelkanth · Airoli / Ghansoli / Koparkhairane | 55 | 6.9% | 3.2% | 4.1% | ₹12,200 est. | ₹79.3 L | Ready |
| Palace Chsl Neelkanth · Kandivali / Borivali / Dahisar | 55 | 6.4% | 3.2% | 4.1% | ₹17,100 est. | ₹1.11 Cr | Ready |
| Samarth Arihant Neelkanth · Kandivali / Borivali / Dahisar | 55 | 6.4% | 3.2% | 4.1% | ₹17,100 est. | ₹1.11 Cr | Ready |
| Vraj Vihar C.H.S.L. Neelkanth · Kandivali / Borivali / Dahisar | 55 | 6.4% | 3.2% | 4.1% | ₹17,100 est. | ₹1.11 Cr | Ready |
| Vishnu Manjula Thanekar (Mmr Sra) CHS Ltd. Neelkanth · Thane East / Kalwa / Mumbra / Diva | 54 | 8.3% | 3.1% | 5.7% | ₹8,950 est. | ₹58.2 L | Under construction Sep 2031 |
| Vaviya Aries Neelkanth · Vashi / Sanpada / Nerul / Belapur | 52 | 6.9% | 3.4% | 4.4% | ₹14,400 est. | ₹93.6 L | Ready |
| Mahavir Krupa CHSL Ltd Neelkanth · Kandivali / Borivali / Dahisar | 52 | 6.8% | 2.7% | 3.7% | ₹16,050 est. | ₹1.04 Cr | Under construction Mar 2027 |
| Neeldhara Neelkanth · Panvel / Ulwe / Dronagiri | 50 | 7.2% | 3.2% | 4.2% | ₹8,000 est. | ₹52.0 L | Ready |
| Neelkanth Shiv Neelkanth · Panvel / Ulwe / Dronagiri | 47 | 9.0% | 4.4% | 7.9% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2030 |
| Adinath Heights Neelkanth · Kandivali / Borivali / Dahisar | 47 | 6.8% | 2.4% | 3.1% | ₹16,050 est. | ₹1.04 Cr | Under construction Mar 2026 |
| D N Heritage Neelkanth · Panvel / Ulwe / Dronagiri | 46 | 8.8% | 4.0% | 6.7% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2029 |
| Neelkanth Elite Neelkanth · Panvel / Ulwe / Dronagiri | 46 | 8.8% | 3.9% | 6.5% | ₹7,500 est. | ₹48.8 L | Under construction Mar 2030 |
| Neelkanth Laxmi Neelkanth · Panvel / Ulwe / Dronagiri | 46 | 8.8% | 4.0% | 6.7% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2029 |
| Neelkanth Stella Neelkanth · Panvel / Ulwe / Dronagiri | 43 | 8.5% | 3.4% | 5.4% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2028 |
| Prime Neelkanth Neelkanth · Panvel / Ulwe / Dronagiri | 43 | 8.5% | 3.4% | 5.4% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2028 |
| Ajit Neelkanth · Panvel / Ulwe / Dronagiri | 43 | 8.5% | 3.4% | 5.4% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2028 |
| Vaviya Seventy 7 Neelkanth · Panvel / Ulwe / Dronagiri | 43 | 8.1% | 2.9% | 4.3% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2027 |
| Neelkanth Complex Neelkanth · Panvel / Ulwe / Dronagiri | 42 | 8.1% | 2.9% | 4.3% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2027 |
| Neelkanth Aspire Neelkanth · Panvel / Ulwe / Dronagiri | 41 | 7.6% | 2.4% | 3.3% | ₹7,500 est. | ₹48.8 L | Under construction Mar 2027 |
| Neelkanth Suryoday Neelkanth · Panvel / Ulwe / Dronagiri | 41 | 7.2% | 3.2% | 4.2% | ₹8,000 est. | ₹52.0 L | Ready |
| Janki Neelkanth · Panvel / Ulwe / Dronagiri | 41 | 7.2% | 3.2% | 4.2% | ₹8,000 est. | ₹52.0 L | Ready |
| Snehshree Neelkanth · Panvel / Ulwe / Dronagiri | 41 | 7.2% | 3.2% | 4.2% | ₹8,000 est. | ₹52.0 L | Ready |
| Neelkanth Auris Neelkanth · Panvel / Ulwe / Dronagiri | 41 | 7.6% | 2.2% | 3.1% | ₹7,500 est. | ₹48.8 L | Under construction May 2027 |
| Samarth Neelkanth · Panvel / Ulwe / Dronagiri | 39 | 7.6% | 2.1% | 2.7% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2026 |
| Shreejis Complex Neelkanth · Dombivli / Palava / Kalyan–Shil Road | 39 | 6.7% | 2.3% | 3.0% | ₹7,000 est. | ₹45.5 L | Ready |
| Shree Ganesh Krupa Co.Op.Hsg Society Ltd Neelkanth · Panvel / Ulwe / Dronagiri | 38 | 8.1% | 2.6% | 3.9% | ₹7,500 est. | ₹48.8 L | Under construction Jun 2028 |
| Cloud 9 Neelkanth · Mumbai region | 38 | 6.6% | 1.2% | 1.6% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2025 |
| Neelkanth Palms Neelkanth · Kalyan / Titwala / Ulhasnagar | 36 | 7.4% | 1.4% | 2.3% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2028 |
| Shraddha Neelkanth · Panvel / Ulwe / Dronagiri | 32 | 7.6% | 2.1% | 2.7% | ₹7,500 est. | ₹48.8 L | Under construction Dec 2025 |
| Neelkanth Royale Palms - F Wing Phase II Neelkanth · Ambernath / Badlapur | 30 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
| Neelkanth Exotica Neelkanth · Panvel / Ulwe / Dronagiri | 29 | 7.6% | 2.1% | 2.7% | ₹7,500 est. | ₹48.8 L | Under construction Jul 2026 |
| Neelkanth Heights CHS Neelkanth · Ambernath / Badlapur | 28 | 6.9% | -0.0% | -0.1% | ₹4,600 est. | ₹29.9 L | Under construction Mar 2027 |
Where Neelkanth builds
Neelkanth compared with other developers
Questions people ask
Is Neelkanth a reliable builder?
MahaRERA filings as of September 11, 2026: 87% of registrations needed no extension; 5 of 30 under-construction projects are past their original completion date by 8 months on average; 6 extensions filed across 5 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Neelkanth project is the best investment?
Neelkanth Cottage in Ghatkopar / Vidyavihar / Vikhroli West scores highest at 64/100 with projected growth 6.4% a year and cash-flow IRR 4.5%. The median Neelkanth project scores 46.
Is Neelkanth delaying possession?
5 under-construction Neelkanth projects are past their original RERA completion date: Cloud 9 (10 months), Shraddha (10 months), West Winds (7 months), Adinath Heights (7 months), Neelkanth Exotica (4 months). Extensions filed with RERA are listed on each project page.
Where does Neelkanth build?
Panvel / Ulwe / Dronagiri, Mumbai (19), Kandivali / Borivali / Dahisar, Mumbai (5), Kharghar / Taloja / Kamothe, Mumbai (3), Airoli / Ghansoli / Koparkhairane, Mumbai (3), Thane West, Mumbai (3), Ghatkopar / Vidyavihar / Vikhroli West, Mumbai (2), Vashi / Sanpada / Nerul / Belapur, Mumbai (2), Ambernath / Badlapur, Mumbai (2) and more. Median price ₹8,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.