Is Peninsula Land a reliable builder?
8 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Peninsula Land in one paragraph
Peninsula Land has a weak delivery record in Karnataka RERA filings: 35% of registrations needed no extension (2 of 8 crawled Bengaluru registrations needed no extension). 3 of 3 under-construction projects are past their original RERA completion date, by 52 months on average (worst 87). The promoter entity carries 12 complaints at K-RERA across its projects. The median Peninsula Land project scores 45/100 on investment merit (below the Bengaluru average); the best, Peninsula Pinewoods Phase - 2, scores 60.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Peninsula Heights Jayanagar / Basavanagudi / Banashankari | 87 | 1 | 100% of schedule · — | 1 | 57 |
| Peninsula Paramount Sarjapur Road | 44 | 1 | 100% of schedule · — | 0 | 23 |
| Peninsula Park Elite Phase III Sarjapur Road | 24 | 0 | 100% of schedule · — | 3 | 36 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Peninsula Land projects
All 8 analysed Peninsula Land projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Peninsula Pinewoods Phase - 2 Peninsula Land · Sarjapur Road | 60 | 10.4% | 6.4% | 9.0% | ₹8,100 est. | ₹97.2 L | Ready |
| Peninsula Heights Peninsula Land · Jayanagar / Basavanagudi / Banashankari | 57 | 9.6% | 4.8% | 6.4% | ₹22,400 est. | ₹3.36 Cr | Under construction Jun 2019 |
| Peninsula Park Elite Peninsula Land · Sarjapur Road | 50 | 10.4% | 6.4% | 9.0% | ₹8,100 est. | ₹97.2 L | Ready |
| Peninsula Park Elite Phase II Peninsula Land · Sarjapur Road | 45 | 10.4% | 6.4% | 9.0% | ₹8,100 est. | ₹97.2 L | Ready |
| Peninsula Prakruthi Phase - 2 Peninsula Land · Sarjapur Road | 44 | 8.9% | 5.8% | 7.6% | ₹14,700 est. | ₹2.21 Cr | Ready |
| Peninsula Solitaire Peninsula Land · Sarjapur Road | 43 | 8.9% | 5.8% | 7.6% | ₹14,700 est. | ₹2.21 Cr | Ready |
| Peninsula Park Elite Phase III Peninsula Land · Sarjapur Road | 36 | 10.8% | 6.9% | 9.8% | ₹7,600 est. | ₹91.2 L | Under construction Sep 2024 |
| Peninsula Paramount Peninsula Land · Sarjapur Road | 23 | 9.3% | 5.0% | 6.6% | ₹13,800 est. | ₹2.07 Cr | Under construction Jan 2023 |
Where Peninsula Land builds
Peninsula Land compared with other developers
Questions people ask
Is Peninsula Land a reliable builder?
Karnataka RERA filings as of September 11, 2026: 35% of registrations needed no extension; 3 of 3 under-construction projects are past their original completion date by 52 months on average; 6 extensions filed across 6 projects; 12 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Peninsula Land project is the best investment?
Peninsula Pinewoods Phase - 2 in Sarjapur Road scores highest at 60/100 with projected growth 10.4% a year and cash-flow IRR 9.0%. The median Peninsula Land project scores 45.
Is Peninsula Land delaying possession?
3 under-construction Peninsula Land projects are past their original RERA completion date: Peninsula Heights (87 months), Peninsula Paramount (44 months), Peninsula Park Elite Phase III (24 months). Extensions filed with RERA are listed on each project page.
Where does Peninsula Land build in Bengaluru?
Sarjapur Road (7), Jayanagar / Basavanagudi / Banashankari (1). Median price ₹13,800 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.