Is Shravanthi a reliable builder?
7 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Shravanthi in one paragraph
Shravanthi has a strong delivery record in Karnataka RERA filings: 78% of registrations needed no extension (6 of 7 crawled Bengaluru registrations needed no extension). 5 of 7 under-construction projects are past their original RERA completion date, by 64 months on average (worst 97). The promoter entity carries 3 complaints at K-RERA across its projects. The median Shravanthi project scores 41/100 on investment merit (below the Bengaluru average); the best, Shravanthi Atmosphere, scores 54.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Shravanthi Palladium Kanakapura Road / Talaghattapura / Banashankari 6th | 97 | 0 | 100% of schedule · — | 1 | 39 |
| Shravanthi Oakridge Kanakapura Road / Talaghattapura / Banashankari 6th | 93 | 0 | 100% of schedule · — | 2 | 37 |
| Shravanthi Pragathi Sarjapur Road | 90 | 0 | 100% of schedule · — | 0 | 40 |
| Shravanthi Prima Bannerghatta Road / JP Nagar / Arekere | 30 | 1 | 100% of schedule · — | 0 | 54 |
| Shravanthi NorthOne Devanahalli / Airport Road / Bagalur | 9 | 0 | 100% of schedule · — | 0 | 41 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Shravanthi projects
All 7 analysed Shravanthi projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Shravanthi Atmosphere Shravanthi · Kanakapura Road / Talaghattapura / Banashankari 6th | 54 | 11.2% | 7.4% | 11.8% | ₹3,900 est. | ₹46.8 L | Under construction Mar 2028 |
| Shravanthi Prima Shravanthi · Bannerghatta Road / JP Nagar / Arekere | 54 | 9.5% | 4.3% | 5.5% | ₹8,000 est. | ₹1.20 Cr | Under construction Mar 2024 |
| Shravanthi NorthOne Shravanthi · Devanahalli / Airport Road / Bagalur | 41 | 11.4% | 7.2% | 10.3% | ₹3,350 est. | ₹40.2 L | Under construction Dec 2025 |
| Shravanthi Prakruti Shravanthi · Electronic City / Hosur Road / Bommasandra | 41 | 8.0% | 2.5% | 3.7% | ₹5,850 est. | ₹68.4 L | Under construction Mar 2028 |
| Shravanthi Pragathi Shravanthi · Sarjapur Road | 40 | 10.0% | 5.5% | 7.0% | ₹8,750 est. | ₹1.44 Cr | Under construction Mar 2019 |
| Shravanthi Palladium Shravanthi · Kanakapura Road / Talaghattapura / Banashankari 6th | 39 | 7.9% | 2.2% | 2.8% | ₹7,300 est. | ₹1.35 Cr | Under construction Aug 2018 |
| Shravanthi Oakridge Shravanthi · Kanakapura Road / Talaghattapura / Banashankari 6th | 37 | 8.1% | 2.1% | 2.7% | ₹7,300 est. | ₹3.03 Cr | Under construction Dec 2018 |
Where Shravanthi builds
Shravanthi compared with other developers
Questions people ask
Is Shravanthi a reliable builder?
Karnataka RERA filings as of September 11, 2026: 78% of registrations needed no extension; 5 of 7 under-construction projects are past their original completion date by 64 months on average; 1 extensions filed across 1 projects; 3 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Shravanthi project is the best investment?
Shravanthi Atmosphere in Kanakapura Road / Talaghattapura / Banashankari 6th scores highest at 54/100 with projected growth 11.2% a year and cash-flow IRR 11.8%. The median Shravanthi project scores 41.
Is Shravanthi delaying possession?
5 under-construction Shravanthi projects are past their original RERA completion date: Shravanthi Palladium (97 months), Shravanthi Oakridge (93 months), Shravanthi Pragathi (90 months), Shravanthi Prima (30 months), Shravanthi NorthOne (9 months). Extensions filed with RERA are listed on each project page.
Where does Shravanthi build in Bengaluru?
Kanakapura Road / Talaghattapura / Banashankari 6th (3), Bannerghatta Road / JP Nagar / Arekere (1), Devanahalli / Airport Road / Bagalur (1), Electronic City / Hosur Road / Bommasandra (1), Sarjapur Road (1). Median price ₹7,300 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.