Total Environment in one paragraph

Total Environment has a weak delivery record in Karnataka RERA filings: 45% of registrations needed no extension (POARR itself slipped several years vs original 2019-20 timelines). 4 of 16 under-construction projects are past their original RERA completion date, by 26 months on average (worst 53). The promoter entity carries 14 complaints at K-RERA across its projects. The median Total Environment project scores 50/100 on investment merit (below the Bengaluru average); the best, A Few Honest Words, scores 62.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.

Projects analysed
18
2 ready · 16 under construction
On-time rate
45%
registrations with no extension filed
Past RERA date
4 / 16
avg 26 months over
Extensions filed
15
8 projects
Promoter complaints
14
K-RERA, across projects
Red flags
33
across due-diligence reports
Median score
50
best 62
Median growth / yr
10.3%
5-yr projection
Median price / sq ft
₹16,300
luxury segment
Litigation declared
12
6 JDA · 2 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
After the Rain- Phase 1
Yelahanka / Jakkur / Airport corridor
533100% of schedule · —439
Learning To Fly
Jayanagar / Basavanagudi / Banashankari
241100% of schedule · —258
After the Rain - Phase II A
Yelahanka / Jakkur / Airport corridor
242100% of schedule · —530
After The Rain-Phase Iib
Yelahanka / Jakkur / Airport corridor
22100% of schedule · 97%133

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Total Environment projects

All 18 analysed Total Environment projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
A Few Honest Words
Total Environment · Jayanagar / Basavanagudi / Banashankari
628.7%4.7%6.4%₹23,100 est.₹9.14 CrReady
In That Quiet Earth Phase 2c
Total Environment · Hennur Road / Kothanur / Kalyan Nagar
6011.1%7.4%13.3%₹13,800 est.₹3.29 CrUnder construction
Mar 2031
Learning To Fly
Total Environment · Jayanagar / Basavanagudi / Banashankari
5810.6%5.3%7.2%₹21,700 est.₹5.92 CrUnder construction
Sep 2024
In That Quiet Earth Phase 2B
Total Environment · Hennur Road / Kothanur / Kalyan Nagar
5410.8%5.9%9.0%₹13,800 est.₹3.57 CrUnder construction
May 2028
Down by the Water
Total Environment · Yelahanka / Jakkur / Airport corridor
5211.2%8.0%14.0%₹16,300 est.₹4.56 CrUnder construction
May 2031
In that Quiet Earth
Total Environment · Hennur Road / Kothanur / Kalyan Nagar
529.8%5.7%7.4%₹14,250 est.₹71.3 LUnder construction
Sep 2026
In That Quiet Earth Phase-2a
Total Environment · Hennur Road / Kothanur / Kalyan Nagar
5110.3%4.9%6.7%₹13,800 est.₹5.73 CrUnder construction
Dec 2026
After The Rain Phase III
Total Environment · Yelahanka / Jakkur / Airport corridor
5111.3%8.9%16.2%₹16,300 est.₹6.46 CrUnder construction
Apr 2032
Lost in the Greens
Total Environment · Bengaluru
508.6%4.3%5.8%₹14,700 est.₹4.34 CrReady
After The Rain Commercial
Total Environment · Yelahanka / Jakkur / Airport corridor
4411.2%7.1%10.7%₹16,300 est.₹2.44 CrUnder construction
May 2028
After The Rain-Phase Iic
Total Environment · Yelahanka / Jakkur / Airport corridor
4410.6%6.5%9.8%₹16,300 est.₹8.65 CrUnder construction
Apr 2028
Pursuit of a Radical Rhapsody
Total Environment · Whitefield
438.0%4.1%5.5%₹19,950₹6.18 CrPartially ready
Dec 2023
In That Quiet Earth Tower 8
Total Environment · Hennur Road / Kothanur / Kalyan Nagar
409.4%7.3%14.2%₹13,800 est.₹5.31 CrUnder construction
Dec 2032
After the Rain- Phase 1
Total Environment · Yelahanka / Jakkur / Airport corridor
3910.9%6.1%8.1%₹16,300 est.₹6.45 CrUnder construction
Apr 2022
After The Rain-Phase Iib
Total Environment · Yelahanka / Jakkur / Airport corridor
3310.3%5.9%7.8%₹16,800 est.₹2.52 CrUnder construction
Aug 2026
After the Rain - Phase II A
Total Environment · Yelahanka / Jakkur / Airport corridor
309.8%5.1%6.9%₹16,300 est.₹6.45 CrUnder construction
Sep 2024
The Magic Faraway Tree Phase 2a
Total Environment · Kanakapura Road / Talaghattapura / Banashankari 6th
267.8%2.0%2.7%₹12,200 est.₹3.01 CrUnder construction
Sep 2026
The Magic Faraway Tree Phase 2
Total Environment · Kanakapura Road / Talaghattapura / Banashankari 6th
227.9%2.1%3.1%₹12,200 est.₹3.01 CrUnder construction
Sep 2027

Where Total Environment builds

Total Environment compared with other developers

Questions people ask

Is Total Environment a reliable builder?

Karnataka RERA filings as of September 11, 2026: 45% of registrations needed no extension; 4 of 16 under-construction projects are past their original completion date by 26 months on average; 15 extensions filed across 8 projects; 14 complaints on the promoter entity at K-RERA; 12 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.

Which Total Environment project is the best investment?

A Few Honest Words in Jayanagar / Basavanagudi / Banashankari scores highest at 62/100 with projected growth 8.7% a year and cash-flow IRR 6.4%. The median Total Environment project scores 50.

Is Total Environment delaying possession?

4 under-construction Total Environment projects are past their original RERA completion date: After the Rain- Phase 1 (53 months), Learning To Fly (24 months), After the Rain - Phase II A (24 months), After The Rain-Phase Iib (2 months). Extensions filed with RERA are listed on each project page.

Where does Total Environment build in Bengaluru?

Yelahanka / Jakkur / Airport corridor (7), Hennur Road / Kothanur / Kalyan Nagar (5), Jayanagar / Basavanagudi / Banashankari (2), Kanakapura Road / Talaghattapura / Banashankari 6th (2), Bengaluru (1), Whitefield (1). Median price ₹16,300 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.

Share on WhatsApp