Is Concorde a reliable builder?
17 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Concorde in one paragraph
Concorde has a mixed delivery record in Karnataka RERA filings: 74% of registrations needed no extension (13 of 17 crawled Bengaluru registrations needed no extension). 6 of 13 under-construction projects are past their original RERA completion date, by 33 months on average (worst 68). The promoter entity carries 2 complaints at K-RERA across its projects. The median Concorde project scores 49/100 on investment merit (below the Bengaluru average); the best, Concorde Neo, scores 74.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Sri Sri Tapovan Kanakapura Road / Talaghattapura / Banashankari 6th | 68 | 1 | 100% of schedule · — | 0 | 34 |
| Concorde Spring Meadows Yeshwanthpur / Tumkur Road / Nagasandra | 38 | 1 | 100% of schedule · — | 0 | 40 |
| Concorde Elements of Earth Kanakapura Road / Talaghattapura / Banashankari 6th | 36 | 0 | 100% of schedule · — | 1 | 36 |
| Concorde Opus II Kanakapura Road / Talaghattapura / Banashankari 6th | 25 | 0 | 100% of schedule · — | 2 | 35 |
| Concorde Luxepolis Bengaluru | 24 | 1 | 100% of schedule · — | 0 | 42 |
| Concorde Opus II Phase 2 Kanakapura Road / Talaghattapura / Banashankari 6th | 5 | 0 | 100% of schedule · — | 0 | 38 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Concorde projects
All 17 analysed Concorde projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Concorde Neo Concorde · Yelahanka / Jakkur / Airport corridor | 74 | 11.3% | 8.2% | 13.6% | ₹10,350 est. | ₹1.12 Cr | Under construction Oct 2029 |
| Concorde Antares Concorde · Yelahanka / Jakkur / Airport corridor | 67 | 10.5% | 7.6% | 11.6% | ₹10,650 est. | ₹69.8 L | Under construction Dec 2028 |
| Concorde Mayfair Concorde · Yelahanka / Jakkur / Airport corridor | 64 | 10.6% | 7.5% | 11.6% | ₹10,350 est. | ₹1.00 Cr | Under construction Nov 2028 |
| Concorde Sienna Concorde · Hennur Road / Kothanur / Kalyan Nagar | 56 | 9.8% | 6.0% | 10.7% | ₹10,350 est. | ₹1.15 Cr | Under construction Jul 2031 |
| Concorde Auriga Concorde · KR Puram / Mahadevapura / Hoskote Road | 55 | 8.2% | 4.6% | 6.0% | ₹10,500 est. | ₹1.25 Cr | Ready |
| Concorde Econex Concorde · Whitefield | 53 | 7.5% | 4.3% | 5.6% | ₹12,500 est. | ₹1.53 Cr | Ready |
| Concorde Eleve Concorde · Hoskote / Budigere Cross / Old Madras Road | 51 | 10.2% | 5.7% | 10.4% | ₹7,350 est. | ₹1.18 Cr | Under construction Dec 2030 |
| Concorde Opus II Phase 3 Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 50 | 10.0% | 5.8% | 8.9% | ₹5,250 est. | ₹61.2 L | Under construction Mar 2027 |
| Concorde Abode 99 Concorde · Attibele / Anekal / Chandapura | 49 | 10.7% | 6.5% | 9.3% | ₹3,350 est. | ₹38.9 L | Under construction Sep 2026 |
| SRI SRI TAPOVAN 2, Block 1 Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 47 | 9.1% | 4.5% | 6.4% | ₹5,400 est. | ₹64.8 L | Ready |
| Concorde Epitome Concorde · Electronic City / Hosur Road / Bommasandra | 42 | 7.6% | 2.9% | 3.8% | ₹7,800 est. | ₹3.01 Cr | Ready |
| Concorde Luxepolis Concorde · Bengaluru | 42 | 9.0% | 3.6% | 4.7% | ₹10,350 est. | ₹2.55 Cr | Under construction Sep 2024 |
| Concorde Spring Meadows Concorde · Yeshwanthpur / Tumkur Road / Nagasandra | 40 | 8.8% | 3.7% | 4.8% | ₹9,200 est. | ₹1.05 Cr | Under construction Jul 2023 |
| Concorde Opus II Phase 2 Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 38 | 9.5% | 5.0% | 7.1% | ₹5,050 est. | ₹58.8 L | Under construction Apr 2026 |
| Concorde Elements of Earth Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 36 | 9.5% | 5.0% | 7.1% | ₹5,050 est. | ₹92.4 L | Under construction Sep 2023 |
| Concorde Opus II Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 35 | 9.5% | 5.0% | 7.1% | ₹5,050 est. | ₹58.8 L | Under construction Aug 2024 |
| Sri Sri Tapovan Concorde · Kanakapura Road / Talaghattapura / Banashankari 6th | 34 | 9.5% | 5.0% | 7.1% | ₹5,050 est. | ₹60.6 L | Under construction Dec 2020 |
Where Concorde builds
Concorde compared with other developers
Questions people ask
Is Concorde a reliable builder?
Karnataka RERA filings as of September 11, 2026: 74% of registrations needed no extension; 6 of 13 under-construction projects are past their original completion date by 33 months on average; 5 extensions filed across 4 projects; 2 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Concorde project is the best investment?
Concorde Neo in Yelahanka / Jakkur / Airport corridor scores highest at 74/100 with projected growth 11.3% a year and cash-flow IRR 13.6%. The median Concorde project scores 49.
Is Concorde delaying possession?
6 under-construction Concorde projects are past their original RERA completion date: Sri Sri Tapovan (68 months), Concorde Spring Meadows (38 months), Concorde Elements of Earth (36 months), Concorde Opus II (25 months), Concorde Luxepolis (24 months) and others. Extensions filed with RERA are listed on each project page.
Where does Concorde build in Bengaluru?
Kanakapura Road / Talaghattapura / Banashankari 6th (6), Yelahanka / Jakkur / Airport corridor (3), Hennur Road / Kothanur / Kalyan Nagar (1), KR Puram / Mahadevapura / Hoskote Road (1), Whitefield (1), Hoskote / Budigere Cross / Old Madras Road (1), Attibele / Anekal / Chandapura (1), Electronic City / Hosur Road / Bommasandra (1) and more. Median price ₹7,800 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.